US Cluster Maintenance
Scheduled Maintenance Report for elastic.io GmbH
Completed
The scheduled maintenance has been completed.
Posted Jan 25, 2021 - 13:13 CET
Verifying
QA is testing the system.
Posted Jan 25, 2021 - 12:57 CET
Update
Last checks on the kubernetes cluster.
Posted Jan 25, 2021 - 12:44 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 25, 2021 - 11:43 CET
Scheduled
Maintenance run on US cluster. No app.elastic.io operations are affected.

This maintenance run is for upgrading some back-end infrastructure to increase processing power due to higher demand from customers.
Posted Jan 25, 2021 - 11:42 CET